DEM-AB-2015-Present-TransCanada-Meter-Station_Redacted

Demolition & Decommissioning, Pipeline Abandonment Services

CLIENTConfidential
LOCATIONAcross Alberta
CONTRACT VALUE>$20,000,000
SCHEDULEStart Date: August 2015
End Date: Present

PROJECT PROFILE

Our company has been executing DDA Programs from 2015 to the Present. This includes meter station, compressor station and side valve decommissioning and demolition as well as decommissioning and abandonment of the associated pipeline laterals. We have completed over 100 sites removing the meter run buildings, instrument buildings, communication towers, cable trays and above and below ground yard piping.

SCOPE OF WORK

All piles were removed or cut off 2.5m below grade and gravel was removed as well. Any redundant fencing was removed and sites were contoured to match existing grades. All associated pipeline laterals were isolated, purged, pigged clean, and capped. Where the pipelines cross under active railways and paved roadways, the sections are filled with concrete for final abandonment.

PROJECT SUCCESS

As the prime contractor on some programs and general contractor for the other multiple programs, our project team was responsible for overall site safety, site supervision, managing sub-trades and maintaining documentation.

We'd Love to Hear From You

Use this form to connect with us

KBL is constantly looking for opportunities to hear from, and work with forward thinking people and organizations. Reach out today!

How can we help you?

Find Out How Partnering with Us Can Truly Make a Difference!

Back