While individuals do their part to reduce their environmental impact, businesses—especially those operating in industrial, remote, or regulated environments—have a greater opportunity and responsibility to lead. Implementing sustainable waste management practices is not only essential for environmental stewardship but also for ensuring compliance, operational efficiency, and long-term business success. This blog explores how sustainable waste […]

PH Adjustment – Nickel Precipitation

PH Adjustment

LOCATION Thompson, MB VALUE $6,650,000 SCHEDULE Start Date: February 2022End Date: December 2022 PROJECT PROFILE The primary purpose of this project is to draw down the water level in Pond # 6 at client site. Secondary purposes include: produce sellable product from the precipitate resulting from the neutralization of pond water; removal of sludge from […]

Construction Water Treatment

Construction Water Treatment

LOCATION Burnaby, BC VALUE $10,400,000 SCHEDULE Start Date: January 2016End Date: Project Ongoing PROJECT PROFILE During the construction phase of the Burnaby terminal, client contacted KBL to manage the water treatment of their systems on site. KBL has since been managing the treatment and discharge of construction water to environment. The primary challenge of treating […]

Landfill Gas Collection System Expansion

LFG Expansion Winnipeg

LOCATION Winnipeg, MB VALUE $3,200,000 SCHEDULE Start Date: June 2020 End Date: March 2021 PROJECT PROFILE The 2020 landfill gas expansion project was the final year/phase of landfill gas work for which KBL had been completing on this site since 2017. The 2020 works were part of a public tender process with KBL being the lowest […]

Bigoray & West Pembina Plant Demolition

Bigoray west Pembina plants

LOCATION Near Drayton Valley, AB VALUE $4,400,000 SCHEDULE Start Date: April 2022 End Date: November 2022 PROJECT PROFILE The project involved technical demolition of all above ground infrastructure on two plant sites no longer required for service including mechanical shearing, torching, and demolition of tanks, vessels, furnaces, stacks, towers, pipe and racks, buildings, etc. The project […]

Hawkeye Facility Abandonment

Hawkeye Abandonment

LOCATION North / Central Alberta VALUE $1,900,000 SCHEDULE Start Date: October 2019 End Date: February 2021 PROJECT PROFILE KBL was selected to complete the full decommissioning and demolition of 13 stand-alone gas plants throughout north-central Alberta.Pipelines were cut and capped at lease boundary and removed off-site. KBL provided excavators, shears, hammers and an assortment of small […]

Pacific Environment Center Site Remediation

Pacific Environment Center Site Remediation

LOCATION North Vancouver, BC VALUE $17,500,000 SCHEDULE Start Date: October 2022End Date: March 2023 PROJECT PROFILE Public Works and Government Services Canada (PWGSC) released their annual tender for the Remedial Excavation Program at the Pacific Environment Centre (PEC) Site remediation, this year, in a two-pronged format to firstly pre-qualify suitable vendors and later issue an […]

Mazeppa Sulphur Pit Removal

Mazeppa Sulphur Pit Removal

CLIENT OWA LOCATION Former Mazeppa Gas Plant, Alberta SERVICES Removal of Elemental Sulphur From a Pit and Demolition of Pit SCHEDULE Start Date: July 2023 End Date: September 2023 PROJECT PROFILE The Mazeppa Gas plant is located near the Hamlet of Mazeppa Alberta approximately 40 km south of Calgary.  The Gas plant began operation in 1986 […]

Hope Bay Sealift

Hope Bay Sealift

CLIENT 2010-2012 – Newmont2013-2016 – TMAC LOCATIONS Hope Bay, NU SERVICES Environmental Projects,  Remediation & Reclamation CONTRACT VALUE $1M Annually SCHEDULE Start Date: 2010End Date: March 2016 PROJECT PROFILE KBL Environmental Ltd (KBL) provided onsite staffing and waste management services for a gold mine operating in Hope Bay, Nunavut over a period of several years. The […]

James Creek Spill Clean-up

James Creek Spill Clean-up

CLIENT Confidential LOCATIONS NT SERVICES Environmental Projects,  Remediation & Reclamation CONTRACT VALUE >$250,000 SCHEDULE Start Date: July 2016End Date: July 2017 PROJECT PROFILE KBL provided spill response, environmental monitoring and sampling following a release of diesel at a highway maintenance camp near Fort Mcpherson, NT. Onsite work including surface water monitoring, product recovery, protection of downstream […]

We'd Love to Hear From You

Use this form to connect with us

KBL is constantly looking for opportunities to hear from, and work with forward thinking people and organizations. Reach out today!

How can we help you?

Find Out How Partnering with Us Can Truly Make a Difference!

Back